Interserve – Building Progress Report Week 43
Interserve Construction are currently completing week 43 of the 48 week build process. We are pleased to report that works are on schedule for the start of the new academic year.
Q3 Langley – Progress Report (May 2016)
Interserve Construction are currently completing week 31 of the 48 week build process. We are pleased to report that works to date are ahead of schedule and achieved water tightness in front of programme dates.
Latest Construction Progress (January 2016)
Construction is well under way at the Q3 Langley site. As you can see from these selection of images, the lift shaft has been erected and the steel work has begun.