Interserve – Building Progress Report Week 43
Interserve Construction are currently completing week 43 of the 48 week build process. We are pleased to report that works are on schedule for the start of the new academic year.
Internally, fixed furniture is complete and final decorations, mechanical & electrical commissioning along with cleaning are on going . Externally, paving is being laid to the front entrance and kerbs installed ready for final tarmac.